Skip to main content Skip to search Skip to main navigation
Experience from countless projects
Let's get started together
We are different. We are better!
Fast and direct contact
Offer
Go to homepage

Partial overhauling of Italpresse IP 750 SC cold chamber die casting machine

Partially overhauled cold-chamber die casting machine

Partially Overhauled Italpresse IP 750 SC Cold-Chamber Die Casting Machine

The Italpresse IP 750 SC, built in 2002, underwent an extensive partial overhaul and maintenance project in which key machine areas were technically inspected and reconditioned. The equipment includes an Italpresse VS-2 ALL metal dosing unit for aluminium die casting.

Manufacturer Italpresse
Model IP 750 SC
Year 2002
Condition Partially overhauled
Machine at a glance

Which Italpresse die casting machine was partially overhauled?

The work was carried out on an Italpresse IP 750 SC cold-chamber die casting machine built in 2002.

The documented work included the clamping unit, toggle system, crosshead, hydraulic ejector, machine bed, cylinders and seals, injection system, hydraulics, wiring, control system, interfaces and safety equipment.

General preparation

Cleaning, dismantling and technical visual inspection

Before the actual repair work began, the machine was cleaned, dismantled and subjected to a visual inspection.

Mechanical components were then inspected and measured to assess the condition of the relevant machine areas.

01 · Cleaning

Prepare the machine for inspection

Contamination is removed so that mechanical areas and wear points can be reliably assessed.

02 · Dismantling

Make assemblies accessible

Relevant components are carefully dismantled so that inspections and repair work can be carried out.

03 · Measurement

Assess the mechanical condition

Mechanical parts are inspected and measured to determine wear and the necessary repair measures.

Clamping unit

New guide columns and reworked clamping platens

One focus of the partial overhaul was the mechanical guidance and die mounting surfaces of the clamping unit.

Guide columns

Four new guide columns

  • 4 new guide columns
  • 4 new front column nuts
  • Inspection of mounting holes
  • Reworking where required
Fixed clamping platen

Machining of the die mounting surface

  • Fixed clamping platen surface-ground
  • Column mounting holes inspected
  • Geometry checked
  • Mounting areas reworked where required
Moving clamping platen

Guides and T-slots reworked

  • Clamping platen face-milled
  • T-slots reworked where required
  • Guide bushings inspected or replaced
  • Slide shoe surfaces inspected
Toggle system

Pins, bushings and guides systematically inspected

The toggle system was comprehensively inspected. Defective guide pins and guide bushings were reworked or replaced.

  • Complete toggle system inspected
  • Defective guide pins reworked
  • Defective guide bushings reworked or replaced
  • Crosshead bores inspected
  • Clamping cylinder mounting inspected
  • Guide components checked
  • Central lubrication system inspected
  • Motorised lubrication functionally tested
Typical work process

From condition assessment to final acceptance

01

Inspection

Clean, dismantle and measure the machine and record its technical condition.

02

Mechanical rework

Rework platens, bores, guides and other relevant machine areas.

03

Component replacement

Replace worn guide components, seals and other stressed components.

04

Assembly

Professionally assemble the reworked assemblies and reintegrate them into the machine.

05

Final inspection

Carry out a trial run with functional testing followed by final customer acceptance.

Crosshead and mould height adjustment

Guide system, column nuts and clamping cylinder reworked

On the crosshead, guide bores, guide pins, guide bushings and components of the central mould height adjustment were inspected.

Guide bores

Inspect and rework bores

The bores for guide bushings were inspected and mechanically reworked where required.

Guide components

Replace pins and bushings

Defective guide pins and guide bushings were replaced and reinstalled.

Mould height adjustment

Inspect column nuts

The column nuts of the central mould height adjustment were inspected and replaced where required.

Clamping cylinder

Inspect cylinder and piston

The clamping cylinder and piston were inspected and, where required, overhauled and fitted with new seals.

Hydraulic ejector

Guide components replaced and hydraulic system resealed

Guidance

Replace pins and bushings

Defective guide pins and guide bushings of the hydraulic ejector were replaced.

Sealing

Reseal the hydraulic ejector

The ejector system was fitted with new seals to restore its hydraulic function.

Machine bed and hydraulics

Tank, guide surfaces and hydraulic connections inspected

  • Hydraulic tank cleaned
  • Guide rail mounting surfaces inspected
  • Mounting surfaces reworked where required
  • Hydraulic pump inspected for wear
  • Pump drive checked
  • Hydraulic line connections inspected
  • System checked for leaks
  • Lines inspected for cracks
Cylinders and seals

Clamping, ejector and injection systems technically reworked

Several hydraulic cylinders and the intensifier were dismantled, measured and resealed.

Dismantling

Inspect cylinders individually

Clamping, ejector and injection cylinders as well as the intensifier were dismantled and measured.

Seals

Replace seals and guide bands

Seals and guide bands were replaced according to the documented maintenance scope.

Resealing

Reseal hydraulic components

Cylinders and the intensifier were professionally resealed after inspection.

Injection system

Injection unit, intensifier and pressure accumulator inspected

The injection system was also part of the documented maintenance scope.

Injection unit

Dismantling and inspection

The complete injection unit was dismantled and inspected for its technical condition.

Intensifier

Rework the piston rod

The intensifier and piston rod were ground and hard chrome plated.

Pressure accumulator

New components with test certificate

A new piston accumulator and pressure vessel were accepted with a test certificate.

Electrical system and controls

Wiring, machine control system and interfaces checked

01

Wiring

Connection cables between the machine and control cabinet were inspected and replaced where required.

02

Control system

The existing machine control system and monitor were inspected.

03

Monitor

A new GEFRAN monitor with software was part of the planned control-system scope.

04

Interfaces

Interfaces to the metal dosing unit, dosing furnace, spraying machine and robot were inspected.

05

Safety

The motorised safety door as well as front and rear protective covers were inspected.

Interfaces

Preparing peripherals for an automated die casting cell

On a used die casting machine, functional interfaces to peripheral equipment are essential for subsequent integration into a die casting cell.

01

Metal dosing unit

Inspect the interface to the Italpresse VS-2 ALL metal dosing unit.

02

Dosing furnace

Check the connection and signal exchange with the dosing furnace.

03

Spraying machine

Inspect the interface for automated die spraying.

04

Robot

Check the robot interface for automated extraction processes.

Painting and refurbishment

Machine and protective areas repainted

Machine

RAL 7035 Grey

The machine components were prepared for painting and subsequently painted in RAL 7035 grey.

Safety equipment

RAL 1004 Yellow

Safety doors and protective covers were painted in RAL 1004 yellow.

Trial run and final inspection

Functional testing before final customer acceptance

After completion of the documented work, the machine underwent a trial run with functional testing. Final acceptance by the customer then took place.

Trial run

Check machine functions

The main machine movements and systems are functionally checked during operation.

Final acceptance

Complete customer acceptance

Following successful functional testing, final documented acceptance by the customer took place.

Shipping preparation

Protect bare machine surfaces against corrosion

Before shipping, bare components were treated with corrosion protection to protect the machined surfaces during storage and transport.

Benefits of a partial overhaul

Why can a partially overhauled die casting machine be economical?

If the basic machine, clamping-force range and equipment concept suit the planned production requirements, a targeted partial overhaul can provide an economical alternative to purchasing a completely new machine.

01

Investment

Existing machine technology can remain in use and be modernised in a targeted manner.

02

Wear

Critical assemblies can be specifically inspected, reworked or replaced.

03

Availability

Depending on the project, an existing machine can potentially be returned to production more quickly.

04

Sustainability

Continued use of industrial machine technology extends the life cycle of existing resources.

The FISS advantage

Overhaul of used cold-chamber die casting machines

FISS supports the technical assessment, inspection, partial overhaul and complete overhaul of used die casting machines.

  • Long-standing experience with die casting machines
  • Technical machine assessment
  • Partial overhaul of individual assemblies
  • Complete overhaul of entire machines
  • Reconditioning of the clamping unit
  • Repair of hydraulic components
  • Machining of clamping platens and guides
  • Inspection of electrical systems and controls
  • Trial run and functional testing
  • Support with dismantling and transport
Frequently asked questions

Questions about the Italpresse IP 750 SC

Which machine was partially overhauled?
An Italpresse IP 750 SC cold-chamber die casting machine built in 2002.
Which additional equipment is included with the machine?
The existing article mentions an Italpresse VS-2 ALL metal dosing unit for aluminium die casting.
Were new guide columns installed?
Yes. Four new guide columns and four new front column nuts were installed.
Were the clamping platens machined?
Yes. The fixed clamping platen was surface-ground and the moving clamping platen was face-milled.
Was the toggle system overhauled?
The toggle system was inspected. Defective guide pins and guide bushings were reworked or replaced.
Was the central lubrication system inspected?
Yes. Defective hoses and lubricant distributors were replaced and the motorised central lubrication system was functionally tested.
What work was carried out on the hydraulic ejector?
Defective guide pins and guide bushings were replaced, and the hydraulic ejector was resealed.
What work was carried out on the injection system?
The injection unit was dismantled and inspected. The intensifier and piston rod were ground and hard chrome plated. A new piston accumulator and pressure vessel were also accepted with a test certificate.
Were the control system and interfaces inspected?
Yes. The machine control system, monitor, wiring and interfaces to the metal dosing unit, dosing furnace, spraying machine and robot were inspected.
Was the machine finally tested?
Yes. The documented maintenance scope includes a trial run with functional testing and final acceptance by the customer.
Have your die casting machine overhauled

Are you planning a partial or complete overhaul of a used die casting machine?

Send FISS the manufacturer, model, year of manufacture, clamping force, machine location, known wear areas, maintenance history, technical documentation and available photos. Our team can support you with condition assessment, partial overhaul, complete overhaul, dismantling and subsequent recommissioning.

Telephone: +49 (0)7181 60696-0   ·   Email: info@fiss-machines.com