Skip to main content Skip to search Skip to main navigation
Experience from countless projects
Let's get started together
We are different. We are better!
Fast and direct contact
Offer
Go to homepage

Dismantling and Transport of Müller-Weingarten S 7300.06.260 press line at Press Shop

Press line successfully dismantled and transported

Dismantling and Transport of the Müller-Weingarten S 7300.06.260 Press Line

FISS successfully completed the dismantling and loading of a Müller-Weingarten S 7300.06.260 press line. The complex heavy-load project included the complete disassembly, packaging and multi-stage transport of the equipment.

Manufacturer Müller-Weingarten
Model S 7300.06.260
Project duration Six months
Heaviest component Press crown up to 250 tonnes
Project at a glance

Which press line was dismantled in the press shop?

The equipment dismantled was a Müller-Weingarten S 7300.06.260 press line. Due to the size and high weight of individual assemblies, the project required careful planning, specialist equipment and cooperation between several technical disciplines.

The complete dismantling process took six months. Handling the press crown, which weighed up to 250 tonnes, was particularly demanding.

Complex heavy-load project

Precise planning for a complete press line

Dismantling a press line is significantly different from dismantling an individual machine. Numerous mechanical, electrical and logistical operations must be completed in a defined sequence.

At the same time, heavy and oversized components must be moved safely, protected, loaded and distributed across different transport systems.

01 · Planning

Coordination of all work stages

Dismantling, lifting technology, packaging and transport were planned as one integrated project.

02 · Specialists

Interdisciplinary project team

Supervisors, electrical engineers, mechanics and packaging specialists worked closely together.

03 · Heavy-load logistics

Transport in several stages

The large components were first transported by heavy-load vehicle and then by ship.

Project team

Which specialists were involved in the dismantling project?

Safely dismantling a press line requires specialists for different technical and organisational tasks.

Project management

Supervision and coordination

The responsible supervisors coordinated work sequences, specialist departments and project deadlines.

  • Coordination of work stages
  • Coordination of specialist personnel
  • Monitoring of project progress
  • Support for safety planning
Electrical engineering

Electrical engineers

Electrical systems and connections had to be disconnected in a controlled manner and prepared for transport.

  • Disconnection of electrical connections
  • Handling of technical interfaces
  • Preparation of electrical components
  • Coordination with the mechanical team
Mechanical work

Experienced mechanics

Mechanical assemblies were disconnected, secured and moved in the planned sequence.

  • Dismantling of heavy assemblies
  • Preparation of lifting operations
  • Securing of moving components
  • Support during loading
Packaging

Packaging specialists

Dismantled components were protected according to their size, weight and transport route.

  • Protection of sensitive components
  • Transport-appropriate packaging
  • Securing of individual assemblies
  • Preparation for road and ship transport
Lifting technology

Heavy-lift specialists

The particularly heavy components were safely lifted using suitable specialist equipment.

  • Planning of lifting points
  • Use of a lifting beam system
  • Controlled lifting
  • Safe positioning
Logistics

Coordination of the transport stages

Road and ship transport had to be coordinated both technically and in terms of scheduling.

  • Planning of heavy-load transport
  • Transport to the Neckar region
  • Transshipment for ship transport
  • Coordination of onward transportation
Project process

From equipment assessment to ship transport

The complete relocation was carried out in coordinated dismantling, lifting, packaging and transport phases.

01

Project planning

The equipment scope, dismantling sequence and required specialist equipment were defined.

02

Dismantling

The individual components of the press line were carefully dismantled over a period of six months.

03

Heavy lifting

The press crown and other large components were lifted using a special lifting beam system.

04

Road transport

The largest components were transported to the Neckar region using heavy-load vehicles.

05

Ship transport

After transshipment, the machine components were transported by ship to their final destination.

Project figures

Key figures for the press line relocation

The project duration, component weight and transport route demonstrate the scale of the project.

6 months

Dismantling period

The complete dismantling of the press line took a total of six months.

250 t

Maximum component weight

The press crown weighed up to 250 tonnes.

2 stages

Transport concept

The large components were transported first by road and then by ship.

Heaviest component

Safe lifting of the press crown weighing up to 250 tonnes

The press crown was one of the most technically demanding components of the project. Its weight made conventional handling impossible.

A special lifting beam system was therefore used for the controlled lift. It distributed the load across suitable lifting points and supported the safe movement of the large component.

Lift planning

Coordinated lifting points

The position, weight and centre of gravity had to be considered before the lift.

Specialist equipment

Lifting beam system

The lifting beam supported controlled load distribution while the press crown was lifted.

Safety

Controlled movement

The lifting operation was carefully coordinated to protect personnel and equipment components.

Dismantling in the press shop

Why did the complete dismantling take six months?

A press line consists of numerous interconnected assemblies, supply lines and control components. These must be disconnected in a controlled manner and divided into transportable units.

  • Assessment of the complete equipment scope
  • Definition of a safe dismantling sequence
  • Disconnection of electrical systems
  • Dismantling of mechanical connections
  • Preparation of heavy assemblies for lifting
  • Protection of sensitive machine components
  • Transport-compatible dismantling of the press line
  • Coordination of multiple specialist departments
  • Packaging of the dismantled components
  • Coordination with heavy-load logistics
Multi-stage transport

From the press shop via the Neckar region to the destination

After dismantling, the press line was transported in several stages. Particularly large components required heavy-load vehicles.

The largest parts were first transported to the Neckar region. From there, onward transport to the final destination was carried out by ship.

Stage 1

Loading in the press shop

The prepared components were loaded onto the designated heavy-load vehicles in a controlled manner.

Stage 2

Heavy-load transport to the Neckar region

The large components were transported by road to the designated transshipment point.

Stage 3

Transshipment of the components

At the waterway, the machine components had to be prepared for the next transport stage.

Stage 4

Onward transport by ship

The press components were transported by water to the final destination.

Packaging and transport protection

Protecting the press components during every transport stage

The packaging had to be suitable for both road transport and the subsequent ship transport.

Sensitive technology

Protection against external influences

Electrical and mechanical components had to be protected against stress during transshipment and transport.

Large components

Securing heavy assemblies

The press crown and other large assemblies were secured against unintended movement.

Transport route

Preparation for road and ship transport

The packaging was adapted to the different requirements of the transport stages.

Success factors

What was essential for the successful press line relocation?

The project required a combination of technical precision, careful coordination and close teamwork.

01

Detailed planning

The individual work and transport phases had to be coordinated at an early stage.

02

Experienced specialists

Different specialists handled the mechanical, electrical and logistical tasks.

03

Suitable lifting technology

Specialist equipment enabled controlled handling of the particularly heavy components.

04

Coordinated logistics

Road and ship transport were organised as one integrated transport chain.

The FISS advantage

Dismantling and heavy-load transport of complex industrial equipment

FISS supports companies with the dismantling, packaging, loading and international relocation of heavy machinery and complete production systems.

  • Long-standing experience with industrial equipment
  • Project planning for complex dismantling projects
  • Coordination of different specialist departments
  • Mechanical and electrical dismantling
  • Planning of demanding heavy-lift operations
  • Use of suitable specialist equipment
  • Professional machine packaging
  • Loading of heavy and oversized components
  • Coordination of road and ship transport
  • One contact for the complete project
Frequently asked questions

Questions about the Müller-Weingarten S 7300.06.260 press line

Which press line was dismantled?
A Müller-Weingarten S 7300.06.260 press line was dismantled.
How long did the dismantling take?
The complete dismantling process took a total of six months.
Which specialists were involved in the project?
The project team included supervisors, electrical engineers, mechanics and packaging specialists.
How heavy was the press crown?
The press crown had a maximum weight of up to 250 tonnes.
How was the press crown lifted?
A special lifting beam system was used for the press crown and other heavy components.
How were the large components transported?
The largest components were first transported to the Neckar region using heavy-load vehicles.
How was the onward transport carried out?
From the Neckar region, the machine components were transported by ship to their final destination.
Why was specialist equipment required?
The size and weight of the press components required specialist lifting and transport equipment for controlled handling.
Does FISS also handle complete press relocation projects?
Depending on the project, FISS can handle planning, mechanical and electrical dismantling, packaging, loading and coordination of onward transport.
Dismantle and transport a press line

Are you planning the dismantling or international relocation of a heavy press or production line?

Send FISS the manufacturer, model, equipment scope, machine weights, dimensions, current location, destination, technical documentation and available photos. Our team will review the requirements and support you with project planning, dismantling, lifting technology, packaging, loading and transport.

Telephone: +49 (0)7181 60696-0   ·   Email: info@fiss-machines.com